2023 State Street Resurfacing Project

The Village has obtained federal aid through the South Suburban Mayor and Managers Association (SSMMA) for roadway improvements along State Street between US Route 6 (162nd St) and Sibley Blvd.  

The project scope consists of pavement resurfacing with hot-mix asphalt, pavement patching, driveway removal and replacement, combination curb and gutter removal and replacement, sidewalk removal and replacement, ADA ramp improvements, drainage and utility structure adjustments/reconstruction, restoration, pavement markings, signage, traffic signal detector loop replacement and all incidental and collateral work necessary to complete the project.

The contractor will require travel lanes be closed at times to facilitate the required improvements. At least 1 travel lane in each direction shall be maintained throughout the project duration.

Some of the driveways within the project limit will be removed and replaced as part of the improvements.  There will be short durations when access to driveways will be impeded while work is being completed. Temporary access to properties will be provided via temporary stone at the close of each working day.  The contractor will provide residents with further notice of the work through door hanger placards, which will be posted prior to work on any driveway. Door hangers will provide further information on timing for anticipated driveway replacements.

The project is scheduled to begin between May 1 and 15, 2023, and will continue through the summer with substantial complete anticipated in August 2023.

Plans Sheet
Location Map
Location Map – Black and White