2023 Street Resurfacing Project

Village of South Holland 
2023 Street Resurfacing Program

General Contractor:  Gallagher Asphalt Corp – 708-877-7160 
Subcontractor: JJ Newell – Concrete – 708-862-1909 
Engineer: Robinson Engineering 
– John Hilsen: 708-359-5548 
– Jay Lauritzen: 708-514-4618 
Public Works Department: 708-339-2323

The scope of work varies throughout the project.  All of the listed areas will have the asphalt milled and removed and a new top coat of asphalt installed.  Some driveway aprons, sidewalks and curbs that are damaged will be replaced.  However, not all driveway aprons, sidewalks and curbs will be replaced.  Robinson Engineering has marked the locations where driveway aprons, sidewalks and curbs need to be replaced. 

Robinson Engineering is aware of existing sprinkler systems and will talk with the concrete contractor before they begin removing sidewalk.  If any get damage occurs during construction the contractor will fix the problem.

Map/Plan for 2023 street resurfacing

List of all locations that will be a part of the 2023 Street Resurfacing Program:

Street

From

To

157th St

9th Ave

LaSalle St

Thornton-Blue Island Rd

Vincennes Rd

West of Van Drunen Rd

Prince Dr

156th St

158th St

Dante Dr

158th St

Dead End

Woodlawn East Ave

159th Pl

162nd St

160th Pl

Minerva Ave

Woodlawn East Ave

Ellis Ave

162nd St

162nd Pl

165th Pl

Woodlawn East Ave

Kimbark Ave

Kimbark Court

167th St

to Dead End

Kimbark Ave

167th St

to Dead End

Kimbark Ave

170th St

172nd St

171st Ct

Kimbark Ave

to Dead End

Clyde Ave

168th St

169th Pl